Week One: 03/29

  • Problematizing Collab/Fab. Background on Twisp Lecture, Discussions and Background Reading -Intro to Scrap Shell Fab

Week two: 04/05

  • Background on Twisp and reseach into Greenhouse design and existing technologies Fieldtrip – depart for Twisp on Friday morning/midday -returning on Sunday Evening

Week three: 04/12

  • Digesting on site collaboration, preparing design ideas for collaborative design charrette Friday/Saturday: Charrette with collaborators in Seattle

Week four: 04/19

  • Design Development Material research amd small mock ups
  • PIN-UP 1

Week five: 04/26

  • Tectonic / Fabrication development of Scaled Prototypes

Week six: 05/03

  • Tectonic Concept Development Possible Fieldtrip – depart for Twisp on Friday morning/midday -returning on Sunday Evening
  • PIN-UP 2

Week seven: 05/10

  • Prototype Refinement

Week eight: 05/17

  • Prototype Fabrication Friday/Saturday: Work Session with collaborators in Seattle

Week nine: 05/24

  • Prototype Fabrication

Week ten: 06/02

  • Prototype Fabrication -completion and preparation for shipping to Twisp

Week eleven: 06/11+06/12

  • FINALS WEEK Friday/Saturday -FinaldeliveryandinstallationofGreenerHouseinTwisp
  • final presentation and exhibition of all course work – sometime during finals week -timing and location T.B.D.
  • Final Design Report due at time of final exhibition

(subject to revision)